Full home renovation in Málaga step by step: process, permits and timelines

How a full home renovation works step by step: construction phases in order, building permits in Málaga (minor vs major works), project duration by square meters, and how to avoid costly delays.

Reformas y Alta Decoración

Apartment in Málaga undergoing full renovation with exposed installations and partition walls in progress

A successful full home renovation follows a disciplined chronological sequence: technical site survey and quote, design and permits, selective demolition, MEP installations, masonry and drywall, tiling and flooring, kitchen and bathroom fitting, fine painting, and final handover. In Málaga and across the Costa del Sol, construction typically takes between 6 and 24 weeks depending on property size, plus license waiting times if structural work is involved. Here is the complete journey, step by step.

What is a full home renovation?

A full home renovation (reforma integral) completely updates an entire residential property: infrastructure, spatial layout, floors, walls, kitchen, and bathrooms. It differs fundamentally from a single-room cosmetic refresh because work spans the whole property, and in almost every case, electrical and plumbing systems are entirely renewed from the ground up.

It represents the gold standard when acquiring an older Spanish apartment or villa to modernize, or when a property has remained un-updated for decades.

The phases of a full renovation, in chronological order

Order is paramount in construction. Each trade sets the exact foundation for the next; skipping sequence or making uncoordinated changes on the fly is the fastest route to costly rework and site delays.

Technical survey and detailed quotation

Everything begins on-site. During the initial technical survey, our team takes laser measurements, examines structural features and existing MEP networks, and scopes your requirements. From this comes an itemized, fixed written quote before a single brick is touched.

Design, spatial planning and material specifications

The new architectural layout is finalized, interior design solutions are refined, and materials are specified: porcelain tiles, sanitaryware, kitchen cabinetry, and custom joinery. The more thoroughly decisions are locked down at this stage, the smoother the construction process. Most delays in Spanish renovations stem from choices deferred while trades are already waiting on site.

Municipal licenses and paperwork

Depending on project scope, we process either a responsible declaration (declaración responsable) or submit for a major works license (licencia de obra mayor) with the local town hall.

Selective demolition and debris removal

Removal of non-retained elements: old partition walls, tiles, sanitary fixtures, redundant plumbing, and false ceilings. Debris is cleared systematically to authorized recycling plants. This is the loudest phase, completely transforming the space within days.

First-fix MEP installations

With walls stripped down, our technicians replace and reroute freshwater plumbing, wastewater drainage, electrical circuitry, communications cabling, and ducted air conditioning. Opening up walls gives full freedom to position light points, sockets, and recessed fixtures exactly where needed.

Masonry, drywall and partition adjustments

New brickwork or plasterboard partitions are erected, self-leveling floor screeds are poured, suspended ceilings installed, and surfaces skimmed. Here the home’s definitive layout takes shape.

Tiling and continuous flooring

Laying porcelain stoneware, natural stone, parquet, or microcement across floors and bathroom walls. Large-format porcelain tiles demand specialized suction gear and leveling systems for millimeter-precise alignment.

Custom carpentry, kitchen and sanitaryware

Installation of interior doors, bespoke wardrobes, kitchen furniture, quartz or porcelain worktops, sinks, taps, shower screens, and toilets. Bespoke carpentry should always be manufactured in advance so delivery coincides perfectly with completed tiling.

Painting and final detailing

Plaster finishing, mist coats, premium washable paint, fitting switchgear, designer lighting, and fine trims that separate a standard job from a high-end architectural finish.

Deep cleaning, client walk-through and warranty

Post-construction industrial cleaning, an itemized final walk-through with the client to verify every detail, and official handover of keys. From this day, your 2-year statutory warranty takes full effect.

Renovation permits in Málaga: what is required?

Navigating Spanish building regulations can feel daunting for international property owners. Broadly speaking, there are two municipal routes:

Minor works (declaración responsable). If the renovation does not alter load-bearing walls, communal risers, or the exterior façade, a responsible declaration is usually sufficient. This process is agile, and work can generally start upon municipal registration.

Major works (obra mayor). If you modify structural walls, change apartment layouts substantially, or alter exterior windows and terraces, you must obtain a formal major works license accompanied by an architect-certified technical project. Municipal approval takes longer and must be factored into your project schedule from the outset.

In addition, consider local construction taxes: the municipal ICIO tax (Impuesto sobre Construcciones, Instalaciones y Obras) is typically a modest percentage of construction costs set by each council. If your apartment belongs to a community of owners (comunidad de propietarios), informing the administrator and respecting communal building bylaws is also essential.

In conservation areas such as Málaga’s historic centre or listed buildings, additional heritage approvals apply. Learn more in our guide to renovation permits in Málaga.

How long does a full home renovation take?

Property Floor AreaEstimated Construction Time
Apartment 60 – 80 m²6 – 10 weeks
Apartment 90 – 120 m²10 – 16 weeks
Home 150 m² or larger16 – 24 weeks

These durations represent active construction time. Where projects require major works licensing, municipal processing periods must be added. This is why licensing is managed in parallel with initial design rather than left until the end.

Renovation delays on the Costa del Sol almost always stem from three causes: selecting materials at the eleventh hour, hidden surprises in ancient uninspected infrastructure, and disjointed subcontractors. The first two are solved through rigorous planning; the third by working with an integrated, in-house team.

How to avoid renovation delays and cost overruns

Lock down material selections early. The vast majority of site delays happen when tiles, bathroom fittings, or kitchen finishes are chosen while trades are already waiting on site.

Insist on a fixed price and signed deadline. Having price and completion dates legally bound in writing eliminates the uncertainty that turns home renovations into stressful experiences.

Work with a single accountable contractor. When one dedicated company coordinates every trade in-house, there are no handoff gaps or finger-pointing. That is where construction days are saved.

Can you live in your property during a full renovation?

During a full home renovation, it is virtually impossible to live on-site: fresh water, power, and sanitary facilities are decommissioned for large stretches of the work. For partial refurbishments, living in another section of the home is often feasible by sealing off work areas with dust barriers.

Planning a full home renovation in Málaga?

Tell us about your property and your vision. We provide a comprehensive on-site survey and deliver a detailed, binding quotation with fixed pricing, clear scope, and guaranteed delivery dates.

Request a quoteHome renovation in Málaga


Reformas y Alta Decoración executes comprehensive property renovations across Málaga and the Costa del Sol with an integrated in-house team, fixed written quote, guaranteed deadline, and 2-year statutory warranty.

Frequently asked questions

A complete overhaul of the property: demolition and site clearance, new plumbing and electrical installations, room distribution, flooring, wall tiling, custom kitchen, modern bathrooms, interior carpentry, and premium painting.

It depends on the project scope. If work does not touch structural members or the building façade, a municipal responsible declaration (declaración responsable) is usually sufficient. Substantial structural changes or layout alterations affecting load-bearing walls require a major works license and an architect's certified project.

Between 6 and 24 weeks of active construction, depending on property size. If the project requires a major works license, municipal approval lead times must be added to the overall calendar.

Site visit and quotation, technical design and permits, demolition, first-fix MEP installations, masonry, tiling and flooring, carpentry, kitchen and bathroom fitting, painting and decorative finishes, followed by deep cleaning and handover.

During a full home renovation, living on-site is almost never practical or recommended because electricity, domestic water, and functioning bathrooms are shut off for significant periods. In partial room renovations, living on-site can be viable by isolating the work area.